โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.11. Example of Project Tracking and ControlEasyโญ๐๐VU๐๏ธVU
Based on the Milestone/Phase table of Project 1880 in Module 05, what were the planned and actual schedule metrics for Phase 2, and what was its final completion status?
A.Planned: 2-Jul to 8-Jul, Actual Start: 2-Jul, Estimated End: 26-Aug, Completion: 100%
B.Planned: 9-Jul to 15-Jul, Actual Start: 18-Aug, Estimated End: 27-Aug, Completion: 100%
C.Planned: 16-Jul to 25-Jul, Actual Start: 27-Aug, Estimated End: 19-Sep, Completion: 80%
D.Planned: 2-Jul to 2-Oct, Actual Start: 25-Jul, Estimated End: 14th November, Completion: 4%
According to Module 05, the Project Management (PM) Framework acts as an integration bridge between which critical organizational departments?
A.Development, Sales, Finance, and Management.
B.Hardware Engineering, Procurement, and Legal Counsel.
C.Human Resources, Marketing, and System Administration.
D.Only the Software Quality Assurance and Code Compiler Teams.
Q3
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.1. Need for Project Management FrameworkEasyโญ๐ก๐๐VU๐๏ธVU
According to CMMI Module 05, what is the primary purpose of adopting a Project Management (PM) Framework in a software development organization?
A.To replace technical engineering processes like verification and validation entirely.
B.To standardize every step of the software development life cycle (SDLC) by developing company-wide consistent artifacts and frameworks.
C.To automate the generation of compiler warning logs and code commits.
D.To eliminate the need for client reviews and feedback loops during requirements gathering.
Q4
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.6. Example of Project PlanningEasyโญ๐ก๐๐VU๐๏ธVU
In the software project planning task spreadsheet shown in Module 05, what is the estimated effort (in man-hours) for the 'Design work' associated with Task 1 ('Add sorting filters all over the listings')?
When establishing a scope baseline directly with the Customer under the PM Framework, who must be invited to the alignment session according to the guidelines?
A.Only the Client and the Project Manager (PM).
B.CEO, Client, Sales Rep, PM, Team Lead (TL), and Vice President of Delivery (VP-Delivery).
C.All software developers, testers, designers, and database administrators.
D.Sales Rep, Accountant, SCM Lead, and Junior Programmer.
Q6
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.11. Example of Project Tracking and ControlEasyโญ๐๐VU๐๏ธVU
Based on the 'Sample Weekly Status Report' of Project 1880 in Module 05, what is the planned start date and planned end date as per the contract, and how do they compare to the actual start date and estimated end date?
A.Planned: 25-Jul to 14th Nov; Actual: 2-Jul to 2-Oct; showing ahead of schedule progress.
B.Planned: 2-Jul to 2-Oct; Actual start was delayed to 25-Jul, and the estimated end date slipped to 14th November.
C.Planned: 2-Jul to 14th Nov; Actual: 25-Jul to 2-Oct; showing on-time execution.
D.Planned: 25-Jul to 2-Oct; Actual start was 2-Jul, and the estimated end date is 14th November.
Q7
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.6. Example of Project PlanningEasy๐๐VU๐๏ธVU
Under Task 4 (Participaid Profile page CMS) of the project planning spreadsheet, what is the status of the 'News widget for frontend' sub-task, and what is its estimated effort?
A.6 hours, WIP (Work in Progress)
B.16 hours, Pending
C.12 hours, Completed
D.3 hours, WIP (Work in Progress)
Q8
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.12. Audit of Each Phase of PM Process AreaMediumโญ๐ก๐๐VU๐๏ธVU
In the Sample Project Audit Report, Project F is rated as 'Weak'. What is the compliance status of Project F across the evaluated project management dimensions that results in this rating?
What is a mandatory prerequisite to software project planning under the CMMI Process Management Process Area according to the handouts?
A.The completion of a functional third-party audit performed by independent assessors.
B.An estimation containing man-hour (and budgetary) requirements to complete the development.
C.Having a 100% bug-free release candidate deployed in a production-ready staging environment.
D.Developing an automated JUnit test suite for all classes and database components.
Q10
โ MCQ๐ CS611๐ Lec 5๐ท๏ธ 05.6. Example of Project PlanningMedium๐โญ๐ก๐๐VU๐๏ธVU
During the planning of the 'Deactivated users module' (Task 2), what critical functional assumption was documented in the comments column to scope the development and testing effort?
A.Assuming that deactivated users can reactivate their accounts via social media logins.
B.Assuming that the module will run on a separate microservice architecture.
C.Assuming that we don't have any deletion and edit function.
D.Assuming that deactivated user data will be archived in CSV format automatically.
๐ Related CS611 - Software Quality Engineering Curriculum Units
Continue practicing topic-wise multiple choice questions from adjacent examination units.